JUNE 7 – JUNE 13, 2025: LOOK AHEAD – CONSTRUCTION ACTIVITY SCHEDULE

SITE
CONSTRUCTED WETLANDS: FINAL CONTROLS & ELECTRICAL CONNECTIONS, PREP & POUR SIDEWALKS
COURTYARD: IRRIGATION SLEEVES, PAVER EDGING, TRENCH DRAINS, MONO BLOCKS
AMPHITHEATER: INSTALL CONDUITS
PROSPECT ST. ENTRANCE: STRUCTURAL SOILS, COBBLESTONES, ROAD PREP, ASPHALT POUR, SITE LIGHTING
BUILDINGS
BUILDING A: FRAMING & DRYWALL, PAINT, TILE, DOORS & HARDWARE, MILLWORK INSTALLATION, LIGHTING, TERRA COTTA
BUILDING B: DRYWALL & TAPING, PAINT, TILE, WOOD FLOORS, LIGHTING, MILLWORK INSTALLATION, DOORS & HARDWARE
BUILDING C: DRYWALL & TAPING, PRIME & FIRST COAT PAINT, LIGHTING, CASEWORK & MILLWORK INSTALLATION
BUILDING C LOWER LEVEL: MECHANICAL, ELECTRICAL EQUIPMENT ONLINE, START UP
WEEKEND WORK
SATURDAY JUNE 7 7 AM – 3 PM

BUILDING A, B, & C: FLOORING, MILLWORK, PAINTING, METAL PANEL, SUNSHADES, TERRA COTTA, MONO BLOCKS, BUILDING & SITE CLEANING