Alerts

JANUARY 11 – JANUARY 17: LOOK AHEAD – CONSTRUCTION ACTIVITY SCHEDULE

SITE
PROSPECT ST: OPEN GATE, POUR HVAC UNIT PADS
WETLANDS: BACKFILL
COURTYARD: UNDERGROUND STORM INSTALLATION

BUILDINGS

BUILDING A: FRAME CORRIDOR SOFFITS, MECHANICAL, ELECTRICAL & PLUMBING ROUGH IN, SLEEPER FLOOR SYSTEM, ELEVATOR INSTALLATION, ROOF & GUTTERS
BUILDING B: FRAME CORRIDOR SOFFITS, MECHANICAL, ELECTRICAL & PLUMBING ROUGH IN, ELEVATOR INSTALLATION, DRYWALL & TAPING
BUILDING C: MECHANICAL, ELECTRICAL & PLUMBING ROUGH IN, WALL & TRUSS INSULATION, WINDOWS, TERRA COTTA SUB FRAMING, ROOF & GUTTERS
BUILDING C LOWER LEVEL: MECHANICAL, ELECTRICAL & PLUMBING ROUGH IN, DRYWALL & TAPING

WEEKEND WORK

SATURDAY, JANUARY 11 7 AM – 3 PM
BUILDING A, B & C: ROOF SOLAR SHINGLE DETAILING, WALL AND TRUSS INSULATION (B&C), REFRIGERANT PIPING & INSULATION (C)