NOVEMBER 16 – NOVEMBER 22: ONE WEEK LOOK AHEAD – CONSTRUCTION ACTIVITY SCHEDULE
SITE
PROSPECT ST: STORMWATER MANHOLES INSTALLATION, INSTALL STREET WATER CONNECTION, LIGHT POLES, CURBS, & ROUGH GRADING
CONSTRUCTED WETLANDS: POUR TRICKLING FILTER PADS
AMPHITHEATER: BACKFILL & REMAINING ELECTRICAL, PREPARE, FORM, & POUR TERRACE STAIRS
BUILDINGS
BUILDING A: MECHANICAL, ELECTRICAL & PLUMBING ROUGH IN, FRAME STAIRS, DRYWALL & TAPING, ROOF GUTTERS & PV ROOF INSTALLATION
TERRA COTTA SUBFRAMING, EXTERIOR WALL AND TRUSS INSULATION
BUILDING B: MECHANICAL, ELECTRICAL & PLUMBING ROUGH IN, DRYWALL & TAPING, ROOF GUTTERS & PV ROOF INSTALLATION, TERRA COTTA SUBFRAMING,
EXTERIOR WALL AND TRUSS INSULATION
BUILDING C: MECHANICAL, ELECTRICAL & PLUMBING ROUGH IN (LOWER LEVEL), TERRA COTTA SUB FRAMING, ROOF GUTTERS & PV ROOF INSTALLATION
WEEKEND WORK
SATURDAY NOVEMBER 16 7AM – 3 PM
BUILDING A, B & C: VAPOR BARRIER, FRAMING SOFFIT AT COURTYARD, IN WALL & PIPE INSULATION
PROSPECT ST: STORM WATER INSTALLATION
Lastest Updates
Contact Us
For construction and site questions please contact:
Bruce McCann
Living Village Project Manager – Yale Divinity School
(203) 432-3349
You must be logged in to post a comment.