MARCH 29 – APRIL 4, 2025: LOOK AHEAD – CONSTRUCTION ACTIVITY SCHEDULE

SITE

CONSTRUCTED WETLANDS: STONE COURSING BACKFILL, DOSING PIPING
COURTYARD: SUNSHADES
EAST ENTRY: STAIR & SIDEWALK PREP AT NORTH SDQ
AMPHITHEATRE: FORM & POUR TERRACE STAIRS

BUILDINGS

BUILDING A: WOOD FLOORS, DRYWALL & TAPING OF SOFFITS, PRIME/FIRST COAT PAINT, TILE, ELEVATOR
BUILDING B: MECHANICAL, ELECTRICAL & PLUMBING ROUGH IN, DRYWALL & TAPING, PRIME/FIRST COAT PAINT, WOOD FLOORS
BUILDING C: DRYWALL & TAPING, ELEVATOR, STAIR WALL INSULATION
BUILDING C LOWER LEVEL: MECHANICAL, ELECTRICAL & PLUMBING ROUGH IN, DRYWALL & TAPING

WEEKEND WORK

SATURDAY, MARCH 29 7 AM – 3 PM
BUILDING A, B, & C: CORRIDOR HIGH CEILINGS, FIREPROOFING, PIPE INSULATION, WALL TAPING, TERRA COTTA (B NORTH), EAST PRECAST