MARCH 29 – APRIL 4, 2025: LOOK AHEAD – CONSTRUCTION ACTIVITY SCHEDULE
SITE
CONSTRUCTED WETLANDS: STONE COURSING BACKFILL, DOSING PIPING
COURTYARD: SUNSHADES
EAST ENTRY: STAIR & SIDEWALK PREP AT NORTH SDQ
AMPHITHEATRE: FORM & POUR TERRACE STAIRS
BUILDINGS
BUILDING A: WOOD FLOORS, DRYWALL & TAPING OF SOFFITS, PRIME/FIRST COAT PAINT, TILE, ELEVATOR
BUILDING B: MECHANICAL, ELECTRICAL & PLUMBING ROUGH IN, DRYWALL & TAPING, PRIME/FIRST COAT PAINT, WOOD FLOORS
BUILDING C: DRYWALL & TAPING, ELEVATOR, STAIR WALL INSULATION
BUILDING C LOWER LEVEL: MECHANICAL, ELECTRICAL & PLUMBING ROUGH IN, DRYWALL & TAPING
WEEKEND WORK
SATURDAY, MARCH 29 7 AM – 3 PM
BUILDING A, B, & C: CORRIDOR HIGH CEILINGS, FIREPROOFING, PIPE INSULATION, WALL TAPING, TERRA COTTA (B NORTH), EAST PRECAST
Lastest Updates
Contact Us
For construction and site questions please contact:

Bruce McCann
Living Village Project Manager – Yale Divinity School
(203) 432-3349
You must be logged in to post a comment.